Contract 84051 REL 20: 2008-104-00 EXP LAND & WATER ACQUISITION
Project Number:
Title:
Upper Columbia Land & Water Acquisition
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
84051 REL 20
Contract Title:
2008-104-00 EXP LAND & WATER ACQUISITION
Contract Continuation:
Previous: Next:
92700: 2008-104-00 EXP LAND & WATER ACQUISITION
Contract Status:
Issued
Contract Description:
This contract includes funding for the purchase of 1,315 acre feet of water from the Cascade Orchard Irrigation Company (COIC), WE: G. This water purchase is made possible by the construction of the COIC Pump back project, WE: H that also provides an 11.9 cfs of additional water in lower Icicle Creek.

This contract also encompasses preacquisition activities for land and water in Columbia River tributary subbasins upstream of Rock Island dam. Acquiring land and water rights to for instream flow enhancement in these areas will protect habitat for ESA-listed salmonids including upper Columbia River (UCR) spring Chinook, UCR summer steelhead and bull trout. This habitat will also benefit non-listed species including summer Chinook, coho salmon, sockeye salmon, and Pacific lamprey.

Based upon available information, candidate parcels and water right will be prioritized using the Upper Columbia Biological Strategy and the recently released Upper Columbia Regional Technical Team – Habitat Action Prioritization within the Upper Columbia River Basin.  In both Okanogan and Methow River subbasins, Ecosystem Diagnosis and Treatment (EDT) information exists as well and will be used to prioritize areas for habitat protection. Other sources of information such as subbasin plans, limiting factors analysis, and empirical data (i.e. redd distribution, groundwater input, etc.) may also guide selection of properties to acquire. Priority will be given to parcels that contain or are adjacent to watercourses with high quality fish habitat but are at risk of degradation due to development potential, and lands that contain or are adjacent to watercourses that provide opportunity for habitat restoration activities that benefit ESA listed fish. At this time the Colville Tribes do not propose to use funds from Project 2008-104-00 for post-acquisition restoration activities. Rather, appropriate restoration or habitat quality improvement projects shall use other sources of funding, potential sources of which are the state Salmon Recovery Funding Board, Priest Rapids Coordinating Committee Habitat Subcommittee, or Habitat Conservation Plan (HCP) Tributary Committee for both Douglas and Chelan County Public Utility Districts, and other BPA funded projects (e.g. Project 2023-001-00).
Account Type(s):
Expense
Contract Start Date:
07/01/2024
Contract End Date:
06/30/2025
Current Contract Value:
$4,140,000
Expenditures:
$634,292

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance Measures Completed as Needed B: 165. CCT - Environmental Compliance 06/30/2025
Projects prioritized based on the most current biological and physical habitat data C: 114. Transaction Development and Facilitation 06/30/2025
Develop and Negotiate water right transactions D: 154. Develop water rights transactions 06/30/2025
Effective implementation management and timely contract administration E: 119. Manage BPA Contracting Requirements 06/30/2025
Acquire water right. F: 164. Upper Columbia Basin Water acquisition 06/30/2025
Complete pre-acquisition activities G: 172. Pre Acquisition Activities 06/30/2025
Acquire water rights from the Cascade Orchards Irrigation Company H: 164. Cascade Orchard Irrigation Company (COIC) Pump back project water purchase 06/30/2025
Complete the construction phase of the COIC pump back project I: 208. Cascade Orchard Irrigation Company (COIC) Pump back project construction 06/30/2025
Completed Annual Report J: 132. Submit Progress Report for the period (7/1/2023) to (6/30/2024) 06/30/2025
Complete the permit level or 60% designs for the PVWUA project K: 175. Loup Loup Creek Irrigation Efficiency Project permit level designs 06/30/2025
Complete the source switch L: 208. Antione Creek Source Switch 06/30/2025
Complete the Selected alternative or 30% design for the Fulton irrigation project M: 175. Complete 30% design drawings for the Fulton Ditch Irrigation Efficiency Project 06/30/2025
Develop (out-year) Prioritized Irrigation Efficiency Study to Attain H20 N: 114. Twisp Valley Power and Irrigation Feasibility Study 06/30/2025

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 2 instances of WE 164 Acquire Water Instream
  • 1 instance of WE 208 Irrigation Infrastructure Construction or Replacement
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 2 instances of WE 114 Identify and Select Projects
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 2 instances of WE 164 Acquire Water Instream
  • 2 instances of WE 208 Irrigation Infrastructure Construction or Replacement
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 208 Irrigation Infrastructure Construction or Replacement

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 CCT - Environmental Compliance
C 114 Transaction Development and Facilitation
D 154 Develop water rights transactions
E 119 Manage BPA Contracting Requirements
F 164 Upper Columbia Basin Water acquisition
G 172 Pre Acquisition Activities
H 164 Cascade Orchard Irrigation Company (COIC) Pump back project water purchase
I 208 Cascade Orchard Irrigation Company (COIC) Pump back project construction
J 132 Submit Progress Report for the period (7/1/2023) to (6/30/2024)
K 175 Loup Loup Creek Irrigation Efficiency Project permit level designs 02/27/2024
L 208 Antione Creek Source Switch
M 175 Complete 30% design drawings for the Fulton Ditch Irrigation Efficiency Project 02/27/2024
N 114 Twisp Valley Power and Irrigation Feasibility Study